Annual Route Changes

Annual Route Changes

Lawrence Transit hosts an annual route change process. Every year, staff looks at routes, ridership data, and schedules and proposes route changes to the bus riding public. In person and virtual survey opportunities are provided to get robust feedback. This page collects all the information you need to engage in this process.

Links

View PDF of all proposed route changes.

2025 Route Change Report 

New Route Features

Route 1: Connecting from Downtown to Haskell campus and adding service on both Haskell and Harper from 19th to 23rd.
Route 3: Serving 9th street. Keeping access to LMH and Heartland.
Route 4: Merging existing Route 4 and Route 10. No longer taking Jayhawk Blvd and instead taking West Campus Rd. Continuing to the 6th St. Walmart, Dillons, and Free State High.
Route 5: Serving Haskell campus from 23rd St. Small timing changes.
Route 6: Returned to staying on 6th street. Will not serve the Merc or Centennial Park.
Route 7: Providing service in both directions along the South Iowa loop, instead of a one-way loop.
Route 8: Serving the center of Haskell campus to provide better access for riders. Returning service to 27th St. for closer access to Prairie Park Elementary School. This route is no longer interlined with Route 10 to improve the schedule.
Route 9: Ending at World Market and no longer making the South Iowa loop. Route will still be interlined with the 7.
Route 11/12: Adopting a ‘B’ schedule. B Schedule will operate on Saturdays, certain holidays, and when KU classes are not in session.
Route 42: Proposed to simplify the route by removing the loops through Lot 90 or at Engineering / Burge Union. Passengers would board along Naismith Drive. Alternate 2 extends the route along Jayhawk Boulevard to the Kansas Union and GSP/Corbin

Public Engagement

Central Station
Paper surveys were available in the lobby in March.

Downtown (7th & Vermont) 
3/10: 9:30am-11:30am
3/14: 12:00pm-2:00pm
3/24: 10am-12:00pm
3/25: 3:00pm-5:00pm
3/26: 12:00pm-2:00pm
3/27: 9:30am-11:30am

Virtual Office Hours 
March 14th – 10:30am – 12:00pm

Status + Timeline + Next Steps

Status

In Progress

Timeline

Project Start: February 2025
Project End: August 20205

Milestone 1: Public Outreach Period (March 2025) – Complete
Milestone 2: Survey data analysis (April 2025) – Complete
Milestone 3: Closing the Loop: Present final routes to the public – Complete
Milestone 4: Ride Guide Production (May 2025 – July 2025) – In progress
Milestone 5: New Routes go into effect (August 2025) – Not started

Next Steps

Public outreach begins in late February – March 31st.

Completed + Supporting Documentation